Construction connectivity for renewable projects

We connect the offices, camps and stores a renewable project uses during construction. It takes about 8 weeks from survey to handover.

Discuss your site

We reply within one working day.

from survey to handover, under our standard programme
About 8 weeks
from survey to go-live on Infinity Power’s Ras Ghareb site
7 weeks
wind farms in Egypt where we delivered construction-phase ICT
5

Figures as of October 2026.

For EPC contractors and owners at mobilization

Engineering, procurement and construction (EPC) contractors buy site connectivity as part of their mobilization scope. PowerChina contracted us for turnkey delivery on three wind farms: Infinity Power’s Ras Ghareb project, Amunet Wind Power and Suez Wind Energy.

Owners also contract it directly. ENGIE did so on Ras Ghareb Wind Energy and Red Sea Wind Energy, and we went on to run IT for both plants.

Once the scope is contracted, the site can be connected before financial close. On Infinity Power’s 200 MW project, we mobilized for PowerChina before financial close, while the site offices were still to be built, so the site had communications from the start of construction.

Our method, step by step

We follow the same steps on every construction site. Each contract sets the details.

  • Step
    1. Site survey
    What happens
    We survey the site and run a line-of-sight study for the microwave link.
  • Step
    2. Wireless design
    What happens
    A predictive Wi-Fi design and an on-site Wi-Fi survey set the access point layout. We issue the layout to the EPC contractor for cabling.
  • Step
    3. Approvals
    What happens
    We coordinate the military and National Telecom Regulatory Authority (NTRA) approvals for the microwave link.
  • Step
    4. Mast and backhaul
    What happens
    We install a 30 m mast and a licensed microwave link from one of the licensed telecom operators we work with. The client contracts the operator directly, and we add no markup to the connection.
  • Step
    5. Separate networks
    What happens
    Each party on site gets its own network segment, wireless network and bandwidth limit. Visitors connect through a captive portal.
  • Step
    6. Site acceptance test (SAT)
    What happens
    We test the installed network before handover.
  • Step
    7. Handover pack
    What happens
    As-built drawings, IP and VLAN inventory, test reports, port matrix and wireless survey report.
  • Step
    8. Managed service
    What happens
    We run the network after handover, as described below.

About 8 weeks from survey to handover

Our standard programme for a construction-site network has four phases.

  • Phase
    1. Survey and approvals
    What happens
    Site survey, line-of-sight study, wireless design and the military and NTRA approvals
  • Phase
    2. Procurement and civil works
    What happens
    We order the equipment and carry out the civil works
  • Phase
    3. Installation
    What happens
    Mast, microwave link, network equipment and access points
  • Phase
    4. Commissioning and handover
    What happens
    SAT, handover pack and the start of the managed service

Each contract sets its own programme. The table shows our standard.

On Infinity Power’s Ras Ghareb site, the network went live 7 weeks after the survey.

Separate networks for each party on site

The owner, the EPC contractor, third parties (such as subcontractors) and visitors each get their own network segment. Each segment has its own wireless network and its own bandwidth limit, so heavy use by one party leaves the others their share. Visitors log in through a captive portal.

Every construction site we have connected has had separate networks for the owner and the EPC contractor, with further networks for subcontractors or guests.

Who does what on a typical site

This is the usual split. Each contract sets the final one.

  • Party
    Senses Innovations
    Usually responsible for
    Site survey and line-of-sight study; wireless design; coordinating the military and NTRA approvals; civil works and the 30 m mast; the active network and access points; SAT and handover pack; the managed service, including fault liaison with the operator
  • Party
    EPC contractor
    Usually responsible for
    Passive cabling to our access point layout, rack space and AC power. On some sites, such as Red Sea Wind Energy, Amunet Wind Power and Suez Wind Energy, we installed the structured cabling as well.
  • Party
    Licensed telecom operator
    Usually responsible for
    The licensed microwave link service and the internet connection
  • Party
    Owner
    Usually responsible for
    Signing the operator’s service agreement and the clearance documents for the approvals

Standard security baseline for site networks

Our standard baseline:

  • separate network segments for each party
  • default credentials changed
  • critical firmware patches applied within 15 days
  • configuration backed up weekly
  • logs kept for 90 days

How we run the site network

  • Item
    Monitoring
    Our standard
    Automated monitoring 24 hours a day, 7 days a week
  • Item
    Incidents
    Our standard
    Handled remotely or on site
  • Item
    Priority 1 incidents
    Our standard
    Acknowledged within 1 hour, at any time
  • Item
    Service hours
    Our standard
    Sunday to Thursday, 9:00 to 18:00 Egypt time, excluding Egyptian public holidays
  • Item
    Maintenance
    Our standard
    Health checks and planned maintenance
  • Item
    Operator faults
    Our standard
    We raise faults with the operator and follow them to resolution
  • Item
    Escalation
    Our standard
    Senses Service Desk, then Service Delivery Manager, then Managing Director
  • Item
    Reporting
    Our standard
    Monthly report on uptime, bandwidth and incidents
  • Item
    On site
    Our standard
    Field team based in Ras Ghareb

Each contract sets its own service levels. On Infinity Power’s Ras Ghareb site, the service level agreement (SLA) target was 99.7%.

Frequently asked questions

How long does it take to connect a construction site?

About 8 weeks from survey to handover under our standard programme. On Infinity Power’s 200 MW site in Ras Ghareb, the network went live 7 weeks after the survey.

Who gets the NTRA and military approvals?

We prepare and coordinate the military and NTRA approvals for the microwave link. The owner signs the clearance documents that the approvals need.

Who contracts the internet operator?

Our client does, usually the owner. The client signs the service agreement with a licensed telecom operator, and we add no markup to the connection. We install the mast and the link equipment, and follow any faults with the operator.

Can the site be connected before financial close?

Yes, once the scope is contracted. On Infinity Power’s Ras Ghareb project, we mobilized before financial close.

How are the owner’s and the EPC contractor’s networks kept apart?

Each party has its own network segment, wireless network and bandwidth limit, and visitors use a captive portal. Every construction site we have connected has had separate networks for the owner and the EPC contractor, with further networks for subcontractors or guests.

What do we receive at handover?

After the site acceptance test (SAT), a handover pack with the as-built drawings, IP and VLAN inventory, test reports, port matrix and wireless survey report.

Plan connectivity for your site

Send the site location, the mobilization date and the parties who need access. We reply within one working day.